2006 Field Season Report for the Hunter – Clyde Watershed Group
Sarah Mattinson, Supervisor


The following is a report on the work that the Hunter – Clyde Watershed Group’s summer crew completed in the summer of 2006. The crew consisted of one supervisor, Sarah Mattinson, for a period of ten weeks, and two crew members, Tom Bulger and Chris Eison, both for a period of 8 weeks. We also had an “Environmental Futures” crew, under the supervision of Otis MacInnis working with us for 10 days.  We also worked with the crew from Trout River supervised by Rob Sharkie for two days, and a crew from Wheatley River for one day.

The crew accomplished many things over the summer. We mainly focused on tree planting, and stream work.

 

Early in the season we planted trees and spent the rest of the summer doing stream work in various areas around the watershed.


Tree Planting

Our tree planting took place early in the summer and was done around the stream to enhance the riparian zone. This is an important part of the stream improvements to our watershed. We planted different types of trees including pine, spruce, birch, elm, and cedar.

 

The Watershed also had a work day on June third. The work day was a great success and 200 trees were planted during the work-day. There were around 25 workers, mostly from the Blue Heron Sea Cadets from North Rustico. Wayne Easter and Carolyn Bertram attended as did a photographer from the Guardian newspaper. Garbage cleanup was also done to improve the stream area. 

 

The tree planting was located on the Ellis property, where we spent approximately four days planting. We planted 400 trees with the ‘Environmental Futures’ group during this time. The trees were at a good size and it was a good time to plant. I’m confident that a majority of our trees will make it.


Stream Work

We spent a majority of the summer doing stream work. Our stream work consisted of cleaning falling and dead trees out of the stream, and making brush mats where necessary. The stream work was mostly focused on one site, Paul Knox’s property, for a majority of the summer. We worked about two kilometres to the left of the bridge. We also took out approximately 5 abandoned beaver dams from that part of the stream. We had help from Rob Sharkie and crew from the Trout River Watershed with a chainsaw for one day to help clear up stream. This was a big help since there was a lot of clearing to be done and some big trees that had fallen down and needed to be taken out. We made approx 20 brush mats in this part of the stream.

We also spent a couple days doing stream work on the Ellis property where we worked to the right of the bridge and made two brush mats.

 

We have started stream work on the Bernard property off of the route 2. They had requested work to be done on the property, so we spent a few days there. We cleared left of the old bridge within eyesight, making a brush mat there as well. To the right of the old bridge, was a beaver dam that had to be removed, we cleared, and we also made a brush mat. There was a lot of debris in this area.

 

Shawn Hill took the crew out on an afternoon to clear out a blockage from the estuary below Moffats Brook. A tree had been blocking the channel, so we went out with the canoes and Shawn helped us with a chain saw, to move the blockage. 

 

A fish passage was also restored at a stream crossing on the Route 2 in the construction zone. The fish passage project was resolved by placing rocks below the culvert barrier thereby raising the water level enough to back water into the hung culvert.  Rocks were supplied by PEI Transportation and Public Works.


Miscellaneous

We also had a group from the Wildlife Conservation Fund arrive to look at the work we have been doing this year. They provide the funding for one of our workers. Andrew and I showed them a sampling of the work we did on the Knox property and also the tree planting area on the Ellis property.

 

It is also interesting to note that while doing stream work on the Knox’s property, a great horned owl was spotted not far from the bridge one morning on our way to work. This shows our great and important the green cover is to this area its wild life.

 

Also, we have been keeping the Hunter – Clyde Watershed group website updated with weekly reports of what the crew has been doing once a week.

 


Accomplishments for the 2006 field season

- Planted approximately 600 trees on the Ellis property
- Cleared and brush matted approximately 2 km of stream
- Removed 5 abandoned beaver dams to help stream flow and fish passage
- Cleared blockage in estuary
- Developed newsletter for the watershed area
- Restored fish passage on the Route 2 construction zone.

 

Recommendations

A few recommendations for the seasons and crews to come:
- More work to be done on the Bernard property. Much clearing and brush mats   are needed.
- A full time crew member who is also a chainsaw operator would be a big help
- More tree planting should be done in different areas around the water shed
- Live beaver dams should be found so that the beavers can be removed as not to build any more dams to block flow.


Acknowledgements

I would like to thank all the organizations and people that have supported this project. Thank you to Andrew Lush and the Hunter – Clyde Watershed board for all their time and effort. Thanks to Shawn Hill for all his help and guidance. This group could not function without the help and support from all people involved. Thanks to all who help support this important community and environmental cause.

 

A Brush Mat that was built on the Knox property

 

A fallen tree being removed from the estuary by Moffat's Brook

 

A Rock Pool by the Highway 2 construction, to aid fish passage

WeeklyReports:

 June 30, 2006

 My name is Sarah Mattinson and I am the supervisor for the Hunter-Clyde watershed this year. I have never done any of this kind of work before, so this being my first week on the job, most of it was just getting to know the area and the type of work that needs to be done. Monday, I spent the morning reading over material that Andrew Lush had given me. I familiarized myself with the reports from last year as well as notes from the meetings of the watershed group. In the after noon, Shawn Hill and Andrew took me around to some of the sites that will be worked on this summer, showing me what was done last year and what work still needs to be done. Tuesday I spend reading materials, figuring out the website as well as heading into town to get a few things that I needed for work.

For a time this year we have the pleasure of working with a young environmentalist group from Charlottetown, lead by Chris McCarthy under the supervision of Otis and with three workers. Since my two workers don’t start until next Tuesday- I started working with the young environmentalists on Wednesday. We planted a truckload of trees along the stream between Wednesday, and Thursday morning. Thursday afternoon we headed to the stream to do stream work. Otis showed us around the stream and taught us how to make brush mats.  We spent Friday morning making brush mats as well.

I’m starting to understand more about the work in the Hunter-Clyde Watershed that will have to be done this summer. We have our work cut out for us!

July 6, 2006

I am doing my weekly report today (Thursday) due to the fact that I will be away tomorrow.

Monday was our Canada Day holiday, so we took the day off. I did however go into town to get some supplies for the crew.

Tuesday was my two workers first day - Chris and Tom are going to be working with me for 8 weeks. We worked on the stream, along with the young environmentalist group, made some brush mats and cleared a major stream blockage.

Wednesday the young environmentalist group worked with us for a couple of hours in the morning. We made a brush mat and cleared another stream blockage. I took Chris and Tom down to look at some of the brush mats that were made previously. We also discovered an old beaver dam upstream that will have to be removed this summer.

Thursday we worked with the young environmentalist group to plant a whole truckload of trees. We planted 200 trees around the stream and surrounding areas and also cleared some areas in the woods to plant trees.

We are getting a lot accomplished, but we still have a lot of work to do!

July 14, 2006

On Monday, we finished a brush mat that Tom and Chris made on Friday, we cleared up to the beaver dam and made a brush mat in the same location where we had planted trees earlier. Tuesday we cleared a place for a brush mat and gathered some stuff for it, and then we found a wasp nest! Then, after doing everything in our power to deter the wasps, we made a brush mat further upstream. Thankfully, no one got stung due to the wasp nest that we disturbed!

On Wednesday, after some running around in the morning, we met Shawn Hill at the stream where the beaver dam is, and discovered that there was more than one beaver dam that will have to be taken out. Shawn and I also walked upstream and after walking up quite a ways we could see some hints to suggest that there is an active beaver dam up stream somewhere, so on another day we will venture up to find out where it is. After showing Shawn around the area, he and I went to Andrew’s house for a bit of a meeting to decide on what work needs to be done for the rest of the summer. Back at the stream in the afternoon, we worked on cleaning the dams out of the stream.

Thursday was rained out. Although we cleared some in the morning finishing clearing out the beaver dams and cutting down some trees in the way, it started to rain quite hard and along the stream was quite cold, so we decided that it was an unsafe environment for working and went home. Friday was much better though. We cleared some more between the beaver dams and upstream. The beavers made quite a mess and killed a lot of trees along the stream and we are taking them out of the stream as to not cause a blockage in the stream later on.

July 21, 2006

This week we have been working away at repairing the stream damage due to the beaver dams that were there. We have been clearing away the dead trees and making brush mats where they were needed.

On Tuesday, Shawn Hill came to see us in the afternoon to check our progress. He also took us upstream and blocked of some areas for brush mats to make it easier to know where they should go. He also mentioned some other tools that we needed for working, which we picked up Wednesday afternoon.

This week has pretty much been a steady daily routine of clearing an area up to a place where a brush mat is needed and making a brush mat. Finding materials for the brush mats is also rather difficult due to the abundance of dead trees and lack of live ones to get brush from, so that takes quite a but of time too.

July 28, 2006

Despite some rain early this week, work proceeded as usual.  We made three brush mats and blocked off a section of stream. We also received our brush axe blades (which Shawn finally found for us). Work is slow because materials are hard to find, but it’s still going pretty good.

Tom also made an alarming discovery on Wednesday afternoon while he took a little walk back stream and found that one of the brush mats we made earlier near one of the old beaver dams, had been attacked by beavers. Originally, Shawn thought that there still might be beavers somewhere upstream, but now with this we know that there really are. That is bad news for the stream, and when Shawn gets off of vacation we will see what his plans are for that.  Luckily none of our other brush mats have been bothered yet, which is good.

Next week we are planning on having a gentleman come in to help us with a chainsaw in return for us to go work for him. It would be a great help for us, since the beavers caused the death of many trees along the stream.

August 4, 2006

We worked right along this week. On Tuesday and Wednesday we had the pleasure of working with a pair from Trout River, Mike and Devin. Mike was skilled with a Chainsaw and helped us clear out our stream on Tuesday, which was a really big help for us. On Wednesday, we went and helped them at Hope River, to clear it out - and we cleared just about all of it.  It was great to be able to have a couple more working with us, and we really appreciate their help!

Luckily none of our other brush mats have been touched by the supposed beavers.  Even though we have cleared quite a way upstream now, and taken out at least 3 more old dams, we have yet to find an active one.

The summer is going by fast and it always seems like there is lots of work to do!

August 11, 2006

 

This week went buy pretty regularly. Monday, Tuesday, and Wednesday were dedicated to making brush mats - averaging one brush mat a day by the time we get all the materials collected.

Wednesday we had the privilege of working with the watershed crew from Wheatley river headed by Simon and another crew of young environmentalists under the supervision of Wade. That provided us with a total of 10 people. With that big of a crew we completed two large brush mats and collected materials for other brush mats. Their help was greatly appreciated and I will be in contact with Simon about working out some days for next week as well.

 

We’ve only got a couple weeks left, and work is going very smoothly.

August 18 2006

 

This week was slow going. We were missing one of our crew, and I have been battling a cold all week. We worked to the best of our ability and continued with stream work on the same part of the stream we have been working on for the last little while. I think Shawn will be visiting tomorrow and he will be showing us another site that needs some work so we will start there.

Next week is our last full week on site!

Last modified July 3, 2007